Monsoon Wind Power Project

Project Background

 

Impact Energy Asia Development Limited (“IEAD”) (previously Impact Energy Asia Limited) entered into a Memorandum of Understanding (“MOU”) with the Government of Lao PDR (“GOL”) in November 2011 to exclusively study the feasibility of large-scale wind projects in three provinces in central and south of Lao PDR. Based on the onsite wind measurement and results of the pre-feasibility study, an area in Dak Cheung district, Sekong Province and Sanxay district, Attapeu Province was considered as the highest potential location for large scale wind development with the potential development scale up to 600 MW. After the pre-feasibility study was approved by the GOL, IEAD was granted exclusive rights to develop the first wind project in Lao PDR under a Project Development Agreement (“PDA”) executed with the GOL on 7 August 2015. The development area covers approximately 68,000 ha with promising wind resource in Sekong and Attapeu provinces.

 

The Project site is located at an elevation of 1,200-1,600m above sea level and is hilly with limited forest and currently limited land use. The Project was officially nominated by the GOL to the Ministry of Industry and Trades of Vietnam (“MOIT”) in July 2017 under a collaboration in the energy sector between Lao PDR and Vietnam, making it the first renewable energy project being offered cross border in ASEAN. On 21 July 2020, the Prime Minister of Vietnam approved the plan for importing power generated from the Project to Vietnam’s power system via a 500kV grid connection and approved the addition of a 500kV transmission line from the Project to the Thanh My Substation to the Revised Power Development Plan VII of Vietnam. The Power Purchase Agreement was successfully executed with Vietnam Electricity (“EVN”) on 12 July 2021 and the Commercial Operation Date is targeted for the end of 2025. 

Key

Development

Milestones

2011

2012

2015

2016

2017

2018

2019

2020

2021

2022

November 2011

MOU executed between the GOL and IEA, which granted IEA exclusive rights to develop a wind farm in a defined 68,000-hectare area and set out the process for IEA to conduct a preliminary Feasibility Study and Environmental, Social, and Health Impact Assessment. 

July 2012

Wind monitoring, with support from an international wind consultant, commenced in Sekong.

August 2015

Based on the preliminary Feasibility Study, IEA identified that Sekong and Attapeu provinces were the most promising areas to develop a large-scale wind project. The Project Development Agreement was executed between the GOL and IEA, which confirmed IEA’s exclusivity to develop the Project.

October 2016

MOU between Governments of Lao PDR and Vietnam for supply of 5,000MW renewable power from Lao PDR to Vietnam

July 2017

The GOL offered the Project’s electricity generation to Vietnam (“Nomination Letter”) and Vietnam formally accepted the nomination under an MOU on cooperation in the energy sector between Lao PDR and Vietnam. 

May 2018

Following the completed and endorsed village and provincial consultations, the draft Environmental, Social, and Health Impact Assessment was submitted to the Ministry of Natural Resources and Environment (“MONRE”) for approval. 

In parallel, IEA commenced engagement with the Institute of Energy of Vietnam to conduct the Grid Impact Study and to identify potential locations for the Project to connect to the Vietnam grid system. 

September 2019

The Grid Impact Study was completed and approved by Vietnam Electricity (“EVN”) and the Ministry of Industrial and Trade (“MOIT”). This confirmed that the Project should connect at 500kV at the Thanh Mi Substation and that there were no negative implications to the Vietnam grid resulting from the Project. 

Following the EVN’s Board Approval, the Tariff MOU was signed, and IEA commenced PPA discussions with EVN. IEA also commenced discussions with Vietnam’s Central Government on the approval process to import power from the Project into Vietnam, which includes obtaining approval from six ministries and ultimately, the Prime Minister’s Office. 

 

July 2020

Following approval by six ministries, the Prime Minister of Vietnam granted approval for the import of power from the Project to Vietnam, which included the required 500kV transmission line in Vietnam’s Power Development Plan. 

IEAD engaged ERM, an international environmental and social consultant, to ensure compliance with international lenders’ safeguard policies. 

July 2021

PPA signed with EVN.

January 2022: Amended and restated PPA signed with EVN.

May 2022: The international ESHIA was successfully disclosed on the Asian Development Bank’s website. 

June 2022: The main text of the Concession Agreement was initialed by the GOL. 

December 2022: Concession Agreement signed with GOL.

Project Site

The Monsoon Wind Power Project is a 600MW wind power project located in the Sekong and Attapeu provinces in Southern Lao PDR. The Project will deliver the generated renewable energy to Central Vietnam through its 500kV transmission line. 

IMG-32432.png

Facts and Figures

950
M USD total Project cost
22
km Transmission Line from substation to Lao-Vietnam border
20
Dedicated Development Members
10
Years of wind measurement
133
Wind Turbine Generators
110
Hub Height
1,000
Ha of Land Use Area
25
Years of Power Purchase Agreement
25
Years of Concession Agreement
meet the team_monsoon wind.jpg

MEET THE TEAM

Nat (2).png

Nat Hutanuwatr

Managing Director

Narut (2).png

Narut Boakajorn

Project Development Director

peter.png

Peter Littlewood

Project Director

Itthipol.png

Itthipol Kanjanaphan

Engineering Director

Chaovalit.png

Chaovalit Khunchaiyaphum

Area Director

Duncan.png

Duncan Black

Commercial and Finance Director

Pavika.png

Pavika Tanveerakasem

Commercial and Finance

Parichat.png

Parichat Thanapatpaiboon

Commercial and Finance

Giang.png

Nguyen Truong Giang

Representative - Vietnam

Kritawit.png

Kritawit Sriwattanapan

Project Development

Shania.png

Shania Pensuk

Project Development

Wattanee (2).png

Wattanee Prungchaiyaphum

Project Development

Kanokploy.png

Kanokploy Phumprasop

Project Development

Sira Khamklai.png

Sira Khamklai

Project Development

Pongpat.png

Pongpat Phukanud

Project Development

Laphaschawan.png

Laphaschawan Plaokaew

Project Accounting

Panassaya Porjit.png

Panassaya Porjit

Financial Controller

Amorn.png

Amorn Vorashompoo

Project Engineer

Siripoom Warathanasin.png

Siripoom Warathanasin

Project Engineer

Vinh.png

Nguyen The Vinh

Project Engineer